Better Rules, Missing Teeth

Better Rules, Missing Teeth

A fair reading of the Public Procurement Rules, 2026

By Ali khan adv – Procurement and public Law

On 28 September 2026 the federal government notified the Public Procurement Rules, 2026. They replace the Public Procurement Rules, 2004, which had governed federal purchasing for more than twenty-two years. The revision follows the Prime Minister’s direction that the framework be brought closer to international practice. A side-by-side reading of the two instruments shows a marked improvement in design. It also shows that the enforcement architecture has not kept pace with the procedural reform.

What has changed

The most consequential shift is that electronic procurement is no longer optional. Under the 2004 Rules an agency might use an electronic system. Rule 8 of the 2026 Rules requires it to use EPADS, the government’s e-procurement platform. Notices, bidding documents, bid opening, evaluation reports and complaints are to pass through that system. An officer who deliberately procures outside, it commits a serious violation. The rule converts a facility into a duty, and treats evasion of the duty as mis-procurement rather than a matter of administrative convenience.

Publicity has been widened in the same spirit. Any purchase above Rs 200,000 must be published on EPADS and on the Authority’s website. Above Rs 5 million it must also be advertised in at least two national newspapers. The threshold logic is sound: low-value work is made visible to the market without the cost of print, while higher-value work still reaches bidders who do not live on the portal.

The Rules also supply methods that the old framework left thin or silent.

  • Gallop tendering is a compressed method for purchases between Rs 700,000 and Rs 2 million, with five days for bids and two days for complaints.
  • Framework agreements for repeat purchases now have defined outer limits: open agreements may run for up to three years, and closed agreements for up to one.
  • A bid carrying an unrealistically low price may be rejected, but only after the bidder has been called upon to explain it. The safeguard is against both predatory pricing and arbitrary exclusion.

Blacklisting has been graded to the gravity of the conduct. The ban may run to ten years for corruption or fraud, to five years for false information, and to six months for failure to perform a contract. The Authority reviews each case, and a ban does not take effect until the bidder has exhausted its legal remedies. That sequencing is important. Debarment is a serious civil consequence. It should follow a finding, not precede a hearing.

Why independent eyes matter

The most valuable structural change is that an office no longer marks its own homework. Under the old practice the same agency often wrote the documents, evaluated the bids, and then heard complaints against its own decisions. The conflict was built into the process. The 2026 Rules break that chain.

Procurement Cells must be staffed by officers accredited by the PPRA. Purchases above Rs 500 million and up to Rs 2 billion must be examined by a Third-Party Validation Committee. Above Rs 2 billion, bids are evaluated by a committee of which at least two-thirds of the members come from outside the procuring agency. Large goods purchases and cross-border deliveries attract independent inspection. Substantial contracts attract independent performance review. The committee that hears complaints is composed entirely of persons from outside the agency.

Equally significant is the new office of Contract Manager. The 2004 Rules had no such role. An agency must now appoint one for each procurement, or for a class of procurement. The Contract Manager keeps the record, monitors performance, ensures that payments and variations follow the Rules, and reports any breach to the head of the agency.

This matters because public procurement most often fails in three places: specification, evaluation and contract administration. A trained and independent pair of eyes is of greatest use at precisely those stages. A clean award followed by an unmanaged contract is not value for money. It is only a deferred dispute.

Where enforcement is still weak

The new Rules explain, with some care, how an agency is to buy. They say much less about what follows when someone does not. Rule 67 distinguishes serious and minor violations. Once a case is characterized as mis-procurement, however, the Rule largely passes the matter on. The head of the agency, or the Authority, may cancel the process or allow it to continue on altered conditions. The case is then referred to “relevant investigating agencies” for disciplinary or criminal action.

The Rules do not identify who is to investigate, within what time, or what follows if nothing is done. There is no separate chapter on penalties for officials, and no clear statement of the Authority’s own power to inspect, inquire and determine. To be fair, the 2004 Rules had the same gap, and dealt with mis-procurement in a single sentence. The comparison does not excuse the omission. Other Pakistani regulators like PTA, OGRA and NEPRA among them are exercising enforcement powers under their parent statutes, including substantial penalties and the suspension or cancellation of licenses. Public procurement moves very large sums of public money therefore it deserves an enforcement limb of comparable strength. A rule that names the wrongdoing and leaves the consequence to someone else is easy to ignore.

After an appeal is won, who gives it effect?

A related difficulty arises on appeal. Under Rule 65(7), a bidder dissatisfied with the complaints committee may go to the Appellate Committee of the Authority. The Committee must decide within forty-five days and may stay the award in the meantime. Its decision is final.

Nothing in the Rules, however, requires the procuring agency to carry that decision into effect within a fixed time, or prescribes the consequence of a refusal or delay. A bidder who has spent months, and money, challenging an unfair award is entitled to a decision that operates in fact, not only on paper. Finality without its Execution is a form of denial.

A few provisions that deserve a second look

Three smaller choices also warrant reconsideration. Under the 2004 Rules, a complaint against a technical evaluation report obliged the committee to stop the process. The new Rule says that it may. The change from a duty to a discretion is not neutral. It restores to the agency a power to press on while the complaint is pending.

The time for appealing a decision of the complaints committee has fallen from thirty days to ten. The minimum period for submission of bids has fallen from fifteen days to ten for national competitive bidding, and from thirty days to twenty for international bidding. Speed is a legitimate objective. Small firms, and firms outside the main commercial centers, may find the compressed calendar difficult to meet. A framework that prizes competition should be careful not to price smaller bidders out of the timetable.

The opinion of the Third-Party Validation Committee is not binding. The head of the agency may depart from it by recording reasons in writing. Publication of those reasons would make the safeguard real. A written departure that is never seen is only a file note.

The balance of the case

None of these reservations displaces the central point. Pakistan has moved from a partly manual system, in which agencies largely supervised themselves, to a framework of compulsory e-procurement, accredited staff, independent review, graded debarment and clearer methods for ordinary purchases. Set against 2004, this is a substantially better instrument.

What remains is to finish the work is a stronger enforcement powers for the Authority, decisions on Appeal that bind in time as well as in form, and published reasons where an agency departs from independent advice, can all be supplied by regulation or by a short amending instrument. None of that undoes the reform. If it is done, these Rules will not merely be better than what they replace. But it will sit comfortably beside the better procurement systems in use elsewhere.